THE CHALLENGE
This LADWP gas-powered generation plant needed a high-performance absorptive sound wall to reduce noise caused by a natural gas transmission facility on their grounds.
Noise levels were reaching 120dBA, and were affecting an adjoining LADWP training facility.
THE SOLUTION
Sound Fighter® Systems (SFS) designed a 3-sided sound enclosure for the facility that effective screened and reduced unwanted noise by over 30dBA.
The noise barrier wall was designed to include double personnel doors as well as pipe cut-outs.
By eliminating the need for a full enclosure, concerns for heat-buildup and air flow were eliminated.
Sound Fighter® provided:
- Detailed Engineered Drawings
- 2000 Panels and Top Caps
- Custom-engineered, hot-dipped galvanized structural steel H-beams, corner beams, door frames and base plates
- Steel acoustical personnel double-door sets
PROJECT — L.A. Department of Water & Power, Los Angeles, CA
CA SALES AGENT — HINS, Inc. 866-348-0833